6H58 0412 Immingham Biomass Lp (Dbc) to Drax Power Station

TrainTimesLive
Menu Close menu

29th August 2026

04:12 – Immingham Biomass Lp (Dbc) → Drax Power Station Arrived -8 Early operated by Not specified (freight or charter)

Reported as far as Drax Power Station · 23 of 23 reporting points · 63 of 63 miles

Calling pattern Timing points only — this train makes no public stops

Calling pattern, including passing points
Booked Actual Route
Location PlatformPlat arrdep arrdep Status Line Path
Immingham Biomass Lp (Dbc) not advertised 0412 0404 -8
Immingham West Junction pass 04160416 pass0408 -8
Humber Road Junction pass 1 min engineering allowance 04200420 pass0413 -7
ULC Ulceby pass 1 0428½0428½ pass0421 -7
Brocklesby Junction pass GLLine 0430½0430½ pass0423 -7 GL
BTB Barnetby pass DGLLine DG 0440½0440½ passno report DGL
Wrawby Junction pass 04430443 pass0435 -8
Scunthorpe F.O.B. Junction pass 2 min engineering allowance 04590459 pass0448 -11
SCU Scunthorpe pass 1 min engineering allowance 2 05060506 pass0453 -13
CWE Crowle pass 2 0520½0520½ pass0506 -14
Thorne Junction pass 1 min engineering allowance 05300530 pass0516 -14
HFS Hatfield & Stainforth pass 1 05330533 pass0519 -14
Thorpe Marsh Junction pass 3½ min pathing allowance 05390539 pass0526 -13
Haywood Junction pass 05450545 pass0530 -15
Knottingley South Junction pass 06030603 pass0547 -16
Knottingley SIG Fe6423 not advertised crew changed 0605½0609 0603 -6
Knottingley East Junction pass 0610½0610½ pass0603 -7
Sudforth Lane Signal Box pass 0616½0616½ pass0608 -8
WBD Whitley Bridge pass 2 06190619 pass0610 -8
HEL Hensall pass 2 06220622 pass0613 -9
Drax Branch Junction pass 06240624 pass0615 -9
Drax Ps Signal D17 pass ½ min pathing allowance 0630½0630½ passno report
Drax Power Station not advertised 0633 0625 -8