How is London Underground running?

Running well. In the last 60 minutes, 100% of 119 station calls were on time. Today so far, 106 trains have arrived, 87.7% on time; 42 cancelled. Which trains were late or cancelled

87.7%On timeof those that arrived
148Trains tracked106 arrived, 42 did not
13Latemore than 5 mins late42Did not run as planned42 cancelled, 0 short
–Unitsin the register
–Seen todayunits that have moved

In the last hour: 119 reports, averaging 0.3 min late.

Punctuality each of the last 14 days

87.7% today, against 94.4% over the 13 days before it.

  1. 12th September 2026: 93.4% on time of 149 trains
  2. 13th September 2026: 98.1% on time of 159 trains
  3. 14th September 2026: 95% on time of 201 trains
  4. 15th September 2026: 93.7% on time of 211 trains
  5. 16th September 2026: 91.8% on time of 189 trains
  6. 17th September 2026: 93.8% on time of 189 trains
  7. 18th September 2026: 95.7% on time of 197 trains
  8. 19th September 2026: 96% on time of 174 trains
  9. 20th September 2026: 95.1% on time of 153 trains
  10. 21st September 2026: 91.7% on time of 196 trains
  11. 22nd September 2026: 95.2% on time of 190 trains
  12. 23rd September 2026: 87.9% on time of 193 trains
  13. 24th September 2026: 99.3% on time of 175 trains
  14. 25th September 2026: 87.7% on time of 148 trains, so far today

Busiest routes booked passenger trains a day, last 7 days

Why trains were cancelled last 7 days

Reason Trains
Delays incurred on non-Network Rail running lines or networks including London Underground 306
Other Passenger Train Operating Company causes 1
Bridge Strike 1

Fleet

The stock register does not cover London Underground, so there is no fleet to list here. The figures above are from the movement feed, which tracks its trains as it does any other operator's.