The railway on 24th August 2026

TrainTimesLive
Menu Close menu

24th August 2026

33,333Trains22,758 carrying passengers
88.2%On timeof those that arrived
2.6 minAverage delayat their last call
1,082Cancelledplanned ones included
24Part cancelledran for only part of the journey
1,329Never activatedbooked, and never appeared
0Stopped shortdid not reach the last stop

By operator least punctual first

OperatorTrackedOn time LateCancelledPart cancelledAverage delay
London North Eastern Railway 199 45.5% 85 43 0 26 min
Avanti West Coast 279 62.7% 100 10 1 12.9 min
Eurostar 28 65.4% 9 2 0 11.7 min
CrossCountry 280 69.8% 75 31 1 10.6 min
Great Northern 396 73.6% 83 82 0 6.9 min
TransPennine Express 320 78.6% 66 10 2 5.3 min
East Midlands Railway 489 80.5% 93 15 0 4.4 min
c2c 242 80.8% 46 3 0 4.8 min
Gatwick Express 74 81.8% 10 18 1 5.6 min
Great Western Railway 1,679 85.6% 231 73 0 3 min
Northern 2,749 87% 346 79 3 2.1 min
Transport for Wales 1,031 87.4% 126 30 0 2.7 min
Thameslink 613 87.7% 64 89 5 2.7 min
Southeastern 1,790 88% 209 41 4 2.5 min
Southern 1,632 88.9% 173 67 1 2.5 min
South Western Railway 1,610 89% 176 13 0 2 min
West Midlands Trains 1,316 89.8% 128 65 3 1.9 min
Greater Anglia 1,143 90.6% 103 51 0 1.5 min
London Overground 1,608 90.9% 123 252 2 1.6 min
Heathrow Express 152 91.2% 13 5 0 2.7 min
London Underground 187 92.6% 11 39 0 1.3 min
Elizabeth line 690 93.9% 41 14 0 1.2 min
Chiltern Railways 346 95.6% 15 2 0 0.7 min
ScotRail 2,282 96.6% 76 19 0 0.8 min
Merseyrail 622 97.2% 17 5 0 0.2 min
South Yorkshire Supertram 37 97.3% 1 0 0 0.6 min
Island Line 52 97.8% 1 7 0 0.8 min
Tyne and Wear Metro 88 98.8% 1 2 0 0.3 min

Punctuality

TrainsRan ArrivedOn time Average delay
Other (5 min) 15,090 15,090 90% 1.4 min
Long distance (10 min) 6,089 6,089 83.7% 5.5 min

Cancellations

KindTrains Share
Attributed 991 91.6%
Unexplained 85 7.9%
Planned 4 0.4%
Reported by Darwin 2 0.2%

Why most common first

ReasonCode Share
Train cancelled at FOC request or planned not to run FL 16.6% (348)
Exclusion commercially agreed and documented between Network Rail and Train Operator PL 10.4% (218)
Delays not investigated by Network Rail OU 9.2% (193)
Fires starting on Network Rail Infrastructure I9 6.8% (143)
Late arrival of booked inward stock YI 5.8% (121)
Uninvestigated Cancellations System Roll-Ups only ZW 5.7% (119)
Overhead line/3rd rail defect I1 2.7% (57)
Bridge Strike XP 2.6% (54)
Track defects other than rail defects IS 2.2% (47)
Delays incurred on non-Network Rail running lines or networks including London Underground TX 2.1% (45)
Track defects other than rail defects IS 1.9% (39)
Late arrival of booked inward stock YI 1.8% (37)
Fatalities or injuries caused by being hit by train XC 1.7% (35)
Train cancelled or delayed at Train Operator's request TB 1.6% (33)
Uninvestigated Cancellations System Roll-Ups only ZW 1.5% (32)
Driver TG 1.4% (30)
Overhead line/3rd rail defect I1 1.3% (27)
Other Passenger Train Operating Company causes TZ 1.1% (23)
Fires starting on Network Rail Infrastructure I9 1% (22)
Fire external to but directly affecting the Network Rail network XL 0.9% (19)
Driver TG 0.9% (19)
Train cancelled or delayed at Train Operator's request TB 0.9% (18)
Broken/cracked/twisted/buckled/flawed rail IR 0.8% (17)
Depot operating problem MU 0.8% (16)
Fire external to but directly affecting the Network Rail network XL 0.7% (15)
Passenger taken ill on train VD 0.7% (15)
Planned underpowered or shortformed service or vehicle MS 0.7% (14)
Other technical failures above the Solebar M8 0.6% (13)
Bridge Strike XP 0.6% (13)
Time lost en-route believed to be Operator cause and information required from Operator TO 0.6% (12)
Confirmed Pantograph ADD, shoe beam or associated system faults M1 0.6% (12)
Trespass including non-intentional XA 0.5% (11)
Other technical failures above the Solebar M8 0.5% (11)
Door and Door system faults M7 0.5% (11)
Trespass including non-intentional XA 0.5% (11)
Broken/cracked/twisted/buckled/flawed rail IR 0.4% (9)
Station evacuated due to fire alarm RH 0.4% (9)
Fatalities or injuries caused by being hit by train XC 0.4% (8)
Vandalism or theft VB 0.4% (8)
Exclusion commercially agreed and documented between Network Rail and Train Operator PL 0.4% (8)

All trains in the network

StateAll Passenger
Arrived 27,361 21,211
Planned 2,542 65
Cancelled 2,101 1,080
Never activated 1,329 402